The SF1 System and the Elgin
Estate
Anthony
Walker
SF1 was a high-rise
housing system designed by a group led by John Davidson in the
London County Council (LCC) Architects' Department and was
intended to bring industrial standards of fabrication to the
housing market at a time when there was enormous pressure to
provide more housing and to do it quickly.
Three estates were proposed as a first contract: the Watney
Estate in Hackney; Tindal Street, Lambeth; and the Elgin Estate
in Westminster. In the event only four blocks were built, two on
the Watney Estate and two on the Elgin Estate. The LCC approved
the purchase of the Walterton Estate, which includes the Elgin
Estate, from the Church Commissioners on 16 December 1952. By
1963 the long leases of nearly 800 dwellings had expired and
reverted to the Council's control as freeholder. These dwellings
were let in about 2500 separate tenancies and occupied by at
least 7000 people but most of them were in a very poor condition
after years of neglect and had a probable life of about ten
years.
The
LCC Architects' Department had been interested in prefabricated
cladding systems for some time. Figure 1 shows an extract from a
handwritten document outlining some of the motivation which led
to their development. Of the proposed blocks, those that were
actually built had a floor layout based on four flats grouped
round a central concrete core with a steelwork frame on a 13ft
4in (4.06m) grid but the system was intrinsically flexible and
could apply to a wide variety of plan forms. The cladding units
were designed to a 6ft 8in (2.03m) module either with or without
a window, and corners were clad with separate asbestos cover
units set at a 450 angle. The cladding panels were of a
composite construction which it was thought would require
minimal external maintenance for at least 20 years. They were
assembled in three-storey units, fully glazed and with internal
finishes ready for final fittings and decoration. An outer skin
of 2.286 mm glass reinforced plastics material (GRP) was filled
with lightweight concrete reinforced with weldmesh, and
separated by a layer of foam to allow for movement. A vapour
barrier was provided and the interior finished with plaster. The
edges of the panels had were reinforced with hollow steel tubes
welded to corner brackets and windows were of aluminium in a
design based on car manufacturing techniques with radiused
corners to allow the use of continuous neoprene gasket glazing
beads. The cladding was to be produced commercially to designs
by the LCC and for which a patent had been applied. One major
problem to be overcome was the question of fire spread and the
architect, John Davidson, proposed exclusive rights to a
supplier for a limited period while a solution was sought, with
the right to a break if this was not achieved within that
period. In 1962 he confirmed that in order to test the panels
properly it would be necessary to manufacture four or five at
the LCCs Wandsworth depot and to erect them on a steel frame.
The whole structure would then be taken to Borehamwood for fire
testing (1). On 9 May it was resolved by the Housing Committee
to spend £2000 from the maintenance account on the patenting ,
production and testing of these panels but by July there was
some disappointment with the fire-retardant performance although
Industrial Exchange Co. had written to say that it still
believed that it would be possible ultimately to achieve the
desired Class 1 certificate.
There
were discussions with other organizations including Jablite
Plastics, Castrol (Tensile Products) and British Industrial
Plastics, but all except Mr Jablonsky of Jablite considered that
the investment for development of the panel would be of the
order of £75 000 - £150 000, a very substantial sum at that
time. Nevertheless the plastics panels were thought to be
essential in reducing the weight of the cladding and so reducing
the cost of the frame and the foundations as well as speeding
construction. It was proposed to continue discussions with
Industrial Exchange but also to meet the Cape/Mickleover
organization. Mickleover had already manufactured some British
Rail relay cabins and gone on to develop a two-storey version
using a steel frame for a telephone exchange which had been
erected in the Bakelite works at Tyseley. The technology had
also been used for laboratories in the Antarctic. The working
party set up to carry out these investigations visited both
companies and reported on 18 October 1962. The main difference
between the two was in their approach to the inhibition of
flame-spread which Industrial Exchange suggested could be
achieved by using mechanically controlled processes for which
fire tests at Fibreglass were reported as promising but details
were not disclosed at that stage. Cape/Mickleover on the other
hand was able to demonstrate its manufacturing processes at its
plant at Colindale where a hand operated depositor was used
together with manual rolling-out in the moulds. The conclusions
drawn from subsequent fire tests carried out at Borehamwood were
that the classification standard required could only be achieved
by pressurized methods of manufacture (Industrial Exchange)
which would give a denser and more uniform laminate. The working
party proposed that an agreement be drawn up with Industrial
Exchange to allow a full-scale fire test to be carried out. In
April 1963 samples of the GRP panels were given by Industrial
Exchange to the LCC Scientific Adviser who carried out tests
including an assessment of their weathering and reported to the
architect in July that year (2). Samples were also submitted to
Yarsley Testing Laboratories who reported in July 1963 that the
material could be classified as Class 1 - very low flame spread.
I ndustrial
Exchange was busy marketing the system and arranged a conference
in June 1963 in London for other city architects as well as
members of the LCC. In July, William Fischbein, later to be
managing director of Indulux, wrote to Kenneth Campbell, LCC's
chief housing architect, reporting on progress and stating that
the enquiries they had received as a result of the conference
indicated that they might indeed recover the heavy investment
they had made. From his letter in August
to John Davidson it was clear that considerable progress had
been made with detailed designs being prepared by the LCC
Architects' Department (3). In September 1963 Hubert Bennett,
Architect to the LCC, confirmed in confidence to the chief
engineer that a consortium was being formed to carry out the
building work. Members were FG Minter, Redpath Brown and
Industrial Exchange (soon to become Indulux) and that the former
was calculating a price.
Promotion at the Building Exhibition
The SF1 system was promoted at the Building Exhibition with a
press release suggesting that a normal seventy-week building
contract could be reduced to 40 using this system. It also
confirmed that Fibreglass Ltd and British Resin Products
(associated with Indulux) were involved. The fire tests were
conducted using a pressure-produced sample from Indulux and
reports 2586/2995 were published in July 1964. The details of
the panels tested differed substantially from those actually
used. In particular a continuous neoprene tube joint which it
was anticipated would be kept under compression was used in an
early test. The actual installation had a simple polysulphide
seal between the adjoining panels.
In
October 1964 the LCC Housing Committee was informed that steel
framed buildings were being investigated using lightweight
cladding for maximum economy. Preliminary costings had been
obtained from Minter and it was anticipated that formal
approvals would be sought for sites at Watney Estate and Tindal
Street before the end of the year. In the meantime approval was
sought for the first two blocks, each of 22 storeys, which would
be erected at Walterton Road, Paddington (the Elgin Estate). In
a concurrent report (Hg 768) permission was sought to negotiate
an offer from FG Minter for the construction of three estates:
Walterton Road, Paddington; Watney Estate, Hackney; and Tindal
Street, Lambeth before the end of the year. There would be about
700 dwellings in total and the large contract was necessary to
justify the investment in plant which would be required. The
proposals were approved and construction started on the Elgin
Estate.
The
first cladding panels were erected on 24 November 1966. Those
for the first block were manufactured in America by the Molded
Fiberglass Company under the supervision of Indulux since this
was the only place where suitable experience of large
machine-matched moulding techniques was available. By the time
panels were required for the subsequent blocks production was
underway at Indulux's works at Luton. By July 1967 Mr Chapman of
the LCC was under pressure to submit an improved programme (5)
and that autumn Horace Cutler, chairman of the Housing
Committee, was able to say that the fabric of a second block
would be complete by end-October with final completion being
programmed to allow occupation by the spring of 1968.
Sadly, there was not to be a happy ending. The Elgin Estate
buildings went through an unhappy period during which the two
blocks named Hermes and Chantry suffered badly in a fire. It was
reported that burnt-out flats were left unrepaired and
undoubtedly little or no action was taken to deal with the known
risks from disintegrating asbestos. In 1984 a report was
commissioned by the Greater London Council (GLC), successor to
the LCC, from Max Lock Easton Perlston & King on the condition
of the Watney Estate including the two tower blocks. The use of
asbestos was found to be widespread and it was noted from
discussion with the GLC that the sprayed fireproofing had become
very friable and would have to be removed. A similar situation
prevailed at Elgin and eventually Walterton & E gin Community
Homes purchased the whole estate with an allocation of money
from Westminster to demolish the tower blocks as the only
realistic means of dealing with the problems.
After this chequered history, the GRP panels were found to be
generally sound and without cracks. There was evidence of
repairs which it was assumed were carried out following a
previous report by the GLC Scientific Branch Buildings Report in
October 1975. The GRP skin had generally separated from the
concrete filling allowing up to 6 mm flexing. The mastic between
the panels was sound but had hardened on the surface and lost
adhesion to the panels in many instances. It was understood that
there had been few cases of water penetration. The fixings were
opened up internally and the work was generally in accordance
with the record drawings except where an asbestos separating
board had been substituted with a tape to separate the RHS
(rolled hollow section) framing and the panels. There were some
signs of deterioration of the steelwork near the edges which
might have been caused by water penetration or condensation.
It
is apparent that the main impetus to developing the system was
to counterbalance the shortage of building resources and
professional manpower. Derek Caswell, a GRP consultant at the
time, comments that even when Indulux had the system ready to
use an interview with Harold Wilson, then a cabinet minister,
was needed before orders were placed which implies that there
were serious misgivings about the system which delayed its
acceptance. The exterior certainly did not live up to the
anticipated maintenance-free finish originally specified, but
the real problem lay not with the cladding but in the amount of
asbestos used internally and the possible long-term fixing
problems, both of which would have necessitated the buildings
being more or less taken to pieces in order to achieve an
acceptable solution. Mike Webb,
however, writing in 1969 soon after the buildings were
completed, considered that they offered a wholly new and
potentially revolutionary form of construction (6). The use of
GRP for the exterior panels undoubtedly played a major part,
allowing cost savings to be made on the structural frame and the
use of three-storey cladding units. Whether or not their loss is
regretted for their architectural merit, they are certainly
worthy of a place in history for their technical innovation. It
was a brave concept which in other circumstances might have
received accolades rather than censure.
References
(1) Memorandum, 8 February 1962.
(2) Memorandum from the LCC' s medical officer of health to the
architect. Weathering was noted as causing some loss of gloss,
rain-spotting and blistering, also reducing scratch resistance
to about a third of its original value. It also caused
appreciable yellowing. 17 July 1963.
(3) Letter, 15 August 1963.
(4) Report from the Architect to the Housing and Town Planning
joint Committee, 1 October 1964.
(5) Notes of a discussion between the Housing, Architects' and
Valuation Departments, 20 July 1967.
(6) Mike Webb, Country Life, 'Architecture in Britain Today',
94,1969.
|